echo Optimisation Objectives

Objectives can be applied to an echo model in order to optimise the behaviour of controllable variables (decision variables) to achieve a certain outcome.

Objective Set

The objective set contains a list of objectives as defined in the sections below. Each objective in the list will be added to a total objective term. Multi-objective optimisation problems are not supported.

Power/Flow Objectives

Power/flow objectives are applied to a port value directly.

Peak Positive Power

This objective penalises the peak positive (imported) power at a port.

Assuming cp1 is a port object, an example of defining this objective is .. code-block:

ppp = PeakPositivePower(component=cp1)

Variables

\(p^+\), port positive component

\(p^\text{max+}\), maximum port positive component

Constraints

\(p^\text{max+} \geq p^+\)

Objective expression

\(O = p^\text{max+}\)

Peak Negative Power

This objective penalises the peak negative (exported) power at a port.

Assuming cp1 is a port object, an example of defining this objective is

pnp = PeakNegativePower(component=cp1)

Variables

\(p^-\), port negative component

\(p^\text{max-}\), maximum port negative component

Constraints

\(p^\text{max-} \leq p^-\)

Objective expression

\(O = p^\text{max-} \cdot -1\)

Quadratic Power

This objective penalises the port power squared. This objective acts as a regularization term. This makes the optimal solution, if there is one, unique.

Assuming cp1 is a port object, an example of defining a quadratic power cost is

quad_cost = QuadraticPower(component=cp1)

Variables

\(p\), port value

Objective expression

\(O = p^2\)

Contingency Negative

This objective maximises the available capacity for an FCAS raise bid. An FCAS raise bid is the power that an asset could export (generate) and deliver upstream.

Parameters

  • path, the path that the flow would theoretically take from the bidder to the upstream grid.

  • duration (\(d\)): duration in seconds that the asset must sustain their bid power.

Variables

\(C^\text{neg}\)

Constraints

The specific constraints will depend on the network. If there are any flow constraints between the bidding port and the upstream port, these need to be accounted for.

Objective expression

Contingency Positive

This objective maximises the available capacity an FCAS lower bid. An FCAS lower bid is a quantity of energy that an asset could import from upstream.

Constraints

The specific constraints will depend on the network. If there are any flow constraints between the bidding port and the upstream port, these need to be accounted for.

Objective expression

Throughput Cost

This objective applies a given rate to the total throughput (import plus export) at a port. If the rate is positive, then throughput will be penalised, and if the rate is negative, throughput will be rewarded.

Assuming cp1 is a port object, an example of defining a throughput cost is

throughput_cost = ThroughputCost(component=cp1, rate=0.000001)

Variables

\(p^+\), port positive component

\(p^-\), port negative component

Parameters

\(r\), rate in $ per flow unit (e.g., $/kW throughput).

Objective expression

\(O = (p^+ - p^-) \cdot r\)

Energy Tariffs

Tariffs apply an array of prices to the energy imported or exported at a given port. Prices should be given in $/kWh, or $/equivalent energy unit for a different commodity.

Import Energy Tariff

This objective applies positive prices to energy imported at a port. Therefore, this objective penalises energy imported at a port.

Assuming cp1 is a port object, an example of defining an import tariff is

import_tariff_array = [0.1] * 28 + [0.3] * 8 + [0.2] * 32 + [0.3] * 16 + [0.1] * 12
import_cost = ImportTariff(component=cp1,
                           tariff_array=import_tariff_array)

Variables

\(p^+\), port positive component

Parameters

\(c_{x, t}\), prices

\(d^\text{interval}\), the time interval in minutes

Objective expression

\(O = p^+ \cdot c \cdot \frac{d^\text{interval}}{60}\)

Export Energy Tariff

This objective applies positive prices to energy exported from a port. This objective maximises the returns (negative costs) from exporting energy from the port.

Assuming cp1 is a port object, an example of defining an export tariff is

export_tariff_array = [0.1] * 28 + [0.3] * 8 + [0.2] * 32 + [0.3] * 16 + [0.1] * 12
export_cost = ExportTariff(component=cp1,
                           tariff_array=export_tariff_array)

Variables

\(p^-\), port negative component

Parameters

\(c_{x, t}\), prices

\(d^\text{interval}\), the time interval in minutes

Objective expression

\(O = p^- \cdot c \cdot \frac{d^\text{interval}}{60}\)

Time of Use Energy Tariffs

Time of use energy tariffs can be formulated as import/export tariffs, by setting the price to zero during the times when the tariff is inactive.

Path Tariff

TBC

Power Tariffs

Demand Tariff

Demand tariffs are composed of a set of demand charges.

A demand charge is a price applied to the maximum power (either import or export) within certain time periods. The demand charge is reset after a certain number of time periods.

For example, consider an import demand charge that applies every evening from 5pm - 8pm, with a rate of $0.5/kW, and resets every month. Each night between 5pm and 8pm, the maximum power imported would be calculated. Then, the maximum of these values would be multiplied by $0.5/kW to obtain the total cost for that month. Then the max value would reset, and the same process would occur for the next month.

Assuming cp1 is a port object, an example of defining a demand tariff and a demand charge is

shoulder_rate = 1.0
shoulder_window = [0] * 18 + [1] * 16 + [0] * 6 + [1] * 4 + [0] * 4

shoulder_charge = DemandCharge(rate=shoulder_rate,
                               window_array=shoulder_window,
                               min_demand=0.0,
                               reset_period=ResetPeriod.Day,
                               import_demand=True)

demand_tariff = ImportDemandTariffObjective(component=cp1,
                                            demand_charges=[shoulder_charge])

Parameters

Each demand charge has the following parameters:

  • window_array (\(w\)): the time window when the charge applies

  • rate (\(r\)): the rate (in $/kW or equivalent for a different commodity)

  • min_demand (\(d^\text{min}\)): the minimum demand

  • reset_period (\(f\)): the reset period frequency (how often the calculation resets)

  • import_demand: parameter for controlling whether the charge applies to imports or exports

The objective penalises the maximum demand (either import or export) in the corresponding time window during each reset period.

Variables

\(p^+\), positive port component (imports)

\(p^-\), negative port component (exports)

Each demand charge has the following variables, which are indexed by the reset period \(f\)

\(d_f\), max demand value

Constraints

For each demand charge and each reset period:

If import_demand is True:

\(d_f \geq (p^+ - d^\text{min}) \cdot w\)

If import_demand is False:

\(d_f \leq (p^- - d^\text{min}) \cdot w\)

Objective expression

If the demand tariff has \(n\) demand charges, then the total objective is:

\(O = \sum_{i=0}^n x_i\)

Where \(x\) is the total cost of each demand charge, and for each demand charge, if import_demand is True:

\(x = \sum_{j=0}^{f} d_j \cdot r\)

else if import_demand is False:

\(x = \sum_{j=0}^{f} d_j \cdot r \cdot -1\)

Other Objectives

Not Fully Charged Penalty

The optimiser will penalise a storage asset for not being fully charged.

Advanced Use

Defining Custom Objectives

If custom objectives are required, they should be added to the optimiser after the optimiser has been initialised. Initialising the optimiser will automatically set the objectives, if any are defined, and so any additional objectives should be added after this initialisation.

optimiser = EchoOptimiser(
                        interval_duration=interval_duration,
                        number_of_intervals=time_periods,
                        number_of_expansion_intervals=expansion_periods,
                        discount_rate=0,
                        ES=system,
                        objective_set=objective_set)

optimiser.objective += sum(getattr(optimiser.model, pv1.port_name)[p, t]
                  for p in optimiser.model.Expansion for t in optimiser.model.Time)

Note the use of +=.